Can a 40 m³/h Concrete Mixer Pump Handle 600 m³ Foundations in Two Weeks?

Table of contents

For bridge projects, contractors often face strict timelines and high-quality requirements. One common question is whether a 40 m³/h pompa mixer beton can deliver enough concrete to cast 600 m³ of foundations within two weeks. Let’s break this down step by step, from output capacity to real-world site conditions, and see if this setup makes sense for your project.
Understanding the Pump’s Output Capacity
The rated capacity of a 40 m³/h mixer pump means it can theoretically deliver 40 cubic meters of concrete per hour. If you work 8 hours per day, the pump can produce and pump about 320 m³ daily. However, real conditions rarely match theoretical values. Site delays, material loading, and equipment maintenance can reduce efficiency. In practice, you may achieve around 25–30 m³/h, which equals about 200–240 m³ per day.
This calculation shows that even at reduced efficiency, the pump has enough potential to meet the requirement. But the question is not only about numbers. It also involves scheduling, manpower, and the site’s logistical setup.
Matching Project Timeline with Concrete Demand
If the bridge foundation requires 600 m³ of concrete in two weeks, you can divide the workload into daily targets. Two weeks usually means 14 days. So the daily average needed is around 43 m³ per day. Compared with the pump’s real capacity of 200 m³ per day, the requirement is very manageable.
Even if work is carried out only 10 days within the two-week window, the average target rises to 60 m³ per day. This is still well below what a 40 m³/h mesin pompa beton can supply. Therefore, the timeline aligns well with the equipment’s ability. The key factor becomes how smoothly the project is organized on-site.
Considering Site Conditions and Manpower
Output capacity alone does not guarantee success. Construction teams must also consider site conditions. For example, foundation casting usually requires continuous pouring without long interruptions. The mixer pump must have a reliable power supply, consistent water and cement feeding, and skilled operators. Without proper coordination, even a high-capacity pump cannot perform efficiently.
Manpower also plays an important role. A team of 6–8 workers is usually enough to handle feeding, monitoring, and finishing tasks. With good scheduling, such a team can keep the mixer pump running steadily, ensuring continuous casting without cold joints in the concrete structure.
Why a Mixer Pump Fits Bridge Projects
Compared to using a separate concrete batching plant and trailer pump, a concrete mixer pump integrates mixing and pumping in one machine. This reduces space requirements on congested bridge sites and simplifies the workflow. Less equipment also means lower fuel and labor costs. For contractors working on mid-scale foundations, this balance of efficiency and convenience makes the mixer pump a practical solution.
Additionally, because bridge projects often take place in remote or narrow locations, bringing in large equipment can be challenging. A 40 m³/h mixer pump is compact and mobile, making it easier to set up close to the pouring area. This reduces delivery time and ensures a stable concrete supply to the foundation.
How to Ensure Continuous Casting Success
Plan Material Supply
Secure stable access to aggregates, cement, and water. Any delay in supply directly impacts pumping continuity.
Maintain Equipment Regularly
Check hydraulic systems, pipelines, and wear parts daily. Preventive maintenance avoids sudden breakdowns during casting.
Coordinate Team Workflow
Assign clear roles to operators, loaders, and finishing workers. Smooth coordination keeps the mixer pump running efficiently.
With these practices, contractors can confidently meet the two-week casting goal using a 40 m³/h concrete mixer pump.
Final Thoughts: Is a 40 m³/h Mixer Pump Enough?
Yes, a 40 m³/h concrete mixer pump is more than capable of supporting continuous casting of 600 m³ foundations within two weeks for a bridge project. Its capacity exceeds the daily requirements, and its compact design fits well with bridge construction sites. The real success, however, depends on project planning, team coordination, and material management.
Why Choose AIMIX for Your Project
At AIMIX, we understand the challenges contractors face in bridge and infrastructure projects. Our concrete mixer pumps are designed with reliable performance, fuel efficiency, and user-friendly operation in mind. We also provide local after-sales service and spare parts support in Indonesia to keep your projects running without delays. If you are looking for equipment that combines mixing and pumping efficiency, AIMIX 40 m³/h concrete mixer pump could be the right solution for your next foundation project.
Contact us today to discuss your project needs and explore the best equipment options for your construction site. Get to know the harga concrete pump at right!
Subscribe to my newsletter
Read articles from Macroadsolutions directly inside your inbox. Subscribe to the newsletter, and don't miss out.
Written by

Macroadsolutions
Macroadsolutions
We are PT. AIMIX GROUP INDONESIA – the local branch of AIMIX in Indonesia. Our mission is to provide reliable construction machinery and local service support to help Indonesian contractors build faster and smarter. We supply a full range of equipment including: Concrete batching plants Self-loading concrete mixers Asphalt mixing plants Stone crushers Concrete pumps With local warehouses, service teams, and spare parts in stock, we respond quickly to your needs – wherever your project is in Indonesia. From machine selection to after-sales support, we’re here to help every step of the way. AIMIX in Indonesia – Local Service, Global Quality.